The Campus Master Plan revision was approved by the California State University Board of Trustees on Sept. 21, 2005. An Environmental Impact Report (EIR) evaluated existing conditions and any changes that may result with implementation of the plan. The EIR proposed mitigation measures to be adopted to avoid significant environmental impacts, where possible. Alternatives to the proposed development concept were also considered in the EIR. Below is a timeline outlining the major milestones in the approval process:

October 2004 – June 2005

Community/stakeholder outreach

November 4, 2004

EIR Public Scoping Meeting

November - December 2004

Draft EIR preparation

January 18, 2005 - March 19, 2005

Draft EIR was available for public review and comment

July 2005

CSU Board of Trustees hearing

September 21, 2005

Decision by CSU Board of Trustees


President Stephen L. Weber's remarks to the CSU Board of Trustees hearing in July 2005:

The Final Environmental Impact Report:

  • Volume 3: Cover Page, Table of Contents & Comment Letters: Part I PDF
  • Volume 3: Cover Page, Table of Contents & Comment Letters: Part II PDF
  • Volume 3: Cover Page, Table of Contents & Comment Letters: Part III PDF
  • Volume 3: Cover Page, Table of Contents & Comment Letters: Part IV PDF
  • Volume 3: Cover Page, Table of Contents & Comment Letters: Part V PDF
  • Volume 3: Cover Page, Table of Contents & Comment Letters: Part VI PDF
  • Volume 3: Cover Page, Table of Contents & Comment Letters: Part VII PDF
  • Volume 3: Cover Page, Table of Contents & Comment Letters: Part VIII PDF
  • Volume 3: Cover Page, Table of Contents & Comment Letters: Part IX PDF
  • Volume 3: Cover Page, Table of Contents & Comment Letters: Part X PDF
  • Volume 3: General Repsonses PDF
  • Volume 4-00: Cover Page and Table of Contents PDF
  • Volume 4-01: Revised Draft EIR Pages PDF
  • Volume 4: Appendix E-1: Historical Site Board Register #80 PDF
  • Volume 4: Appendix M-1: Del Cerro Roadway Classifications: Part I PDF
  • Volume 4: Appendix M-1: Del Cerro Roadway Classifications: Part II PDF
  • Volume 4: Appendix M-1: Del Cerro Roadway Classifications: Part III PDF
  • Volume 4: Appendix M-2: Waring Road Extension Feasibility PDF
  • Volume 4: Appendix Q: City of San Diego Will Serve Letter PDF
  • Volume 4: Appendix P: Public Outreach Materials PDF
  • Volume 4: Appendix R: Letter from Smoke Tree Adobe Falls Owners Association PDF
  • Volume 4: Appendix S: Additional Letters Received in Support of the SDSU 2005 Campus Master Plan Revision PDF
  • Volume 4: Appendix T: Grantville Redevelopment Project EIR PDF
  • Volume 4: Appendix U: Assessment of Faculty & Staff Housing Issues PDF

  • CEQA Findings of Fact and Statement of Overriding Considerations PDF
  • Mitigation Monitoring And Reporting Program PDF

If you have questions, contact:

Anthony Fulton, Director
Facilities Planning & Management
Division of Business and Financial Affairs
San Diego State University
5500 Campanile Drive
San Diego, CA  92182-1624

Back to Top